ClientTaisei Corporation,Japan
Project Completion Date:2005
Capacity300 MW ( Power Plant ) – 86.000 m³/day ( Desalination Plant )
ContractorAlarko Contracting Group ( Alsim )
Description of the ProjectThe construction project consists of procurement and execution of all civil works of the Desalination and Power Plant and Water Intake Structure and construction works of the plant and utility buildings.

Main quantities of the project are :
Earthworks : 850.000 m³
Reinforced concrete : 50.000 m³
Sheet piling : 6.000 m²
Asphalt roads : 45.000 m²