ClientTCDD (General Directorate of Turkish State Railways)
ContractorAlarko Contracting Group (Alsim) – SEL A.G., Germany –
Iskra Commerce, Yugoslavia

Description of the Project

The turn-key Project consisted of the engineering, procurement and execution of the railway signalization between the stations of Kayas and Hanli (530 km) and between the stations of Hanli and Cetinkaya (225 km). The project was carried out for 120 km/hour of train speed. The number of the stations between Kayas-Hanli was 44 and the number of the stations between Hanli and Cetinkaya was 17. An automatic train stop system, a central traffic control system and an automatic block system were included in the project.