ClientIGSAS (Istanbul Fertilizer Industry)
ConsultantJohn – Zink, UK
Capacity1.200.000 kcal/hour
ContractorAlarko Contracting Group (Alsim)

Description of the Project
The Project consisted of the retubing of 2 superheaters, x-raying of all the welds, heat processing at 700°C as well as hydrostatic testing at a pressure of 162 bars. The above-mentioned superheaters were within a wasteheat boiler with a capacity of 210 tons/hour steam, at a pressure of 134 bars and a temperature of 505°C.