ClientALTEK A.S. 
(Power Plants Construction, Operation & Trading Company Inc.)
Project Completion Date2010
Capacity81.99 MW
ContractorAlarko Contracting Group (Alsim)

Description of the ProjectThe turn-key Project consists of the engineering, procurement and execution of all civil, mechanical and electrical works and erection of all the equipments of the natural gas combined cycle power plant with a capacity of 81.99 MW. The plant has two combustion turbines (PRATT&WITTNEY FT8-3 SWIFTPACK) with a total capacity of 60 MW, two number of Once Through Steam Generators are located behind the gas turbines and driving the one condensing steam turbine generator with a capacity of 22 MW.